Action | Progress | Next steps | Comments |
---|---|---|---|
Planning in detail (end feb/start of mars) VC | Set date for VC | SCB,ISTAT,INSEE,SSB | |
Setup google-drive documents and share plus share prezi | SCB | ||
Setup the general structure of the documents | SCB | ||
During hackathon in Rome try to capture materials for scenarios in cookbook | SCB | ||
Translate the scenarios to the cookbook | SCB | ||
Build first draft of cookbook based on materials from hackaton | SCB | ||
Deliver draft of cookbook in May | SCB | ||
Work on architectural recomendations | SCB | ||
Work on interactive guidence | SCB | ||
Test the current output during modernstats world workshop | SCB | ||
Deliver draft of arch guidance in July | SCB | ||
VC with WP2 members in August | SCB,ISTAT,INSEE,SSB | ||
Between july and december - add guidance and scenarios based on experience and the work done in WP1 and WP3 | SCB | ||
Align deliverables and deliver draft versions in dec 2019 | SCB | ||
Setup indicators for test of usability in January 2020 | SCB | ||
Test the deliverables using developers and architects that are not part of the work and get feedback in January 2020 | SCB,ISTAT,INSEE,SSB | ||
Align WP2 deliverables with all other WPs in M14 | SCB,ISTAT,INSEE,SSB | ||
Continued work on adding guidance, cookbook scenarios and interactive guidance M13-M18 | SCB | ||
Align deliverables and deliver Drafts M13-M18 | SCB | ||
Perform second test on deliverables M18 | SCB |